AIFA – LECHERÍA SUBURBAN TRAIN

CLIENT:
CAF Turnkey & Engineering SL

CONTRACT AMOUNT:
362.44 Million MXN

DESCRIPTION:
Execution of works corresponding to the following systems:

Station auxiliary substations, inspection area, and CETRAMs (Modal Transfer Centers): Supply, assembly, testing, and commissioning of the equipment integrating the substations.

23 kV Loop: Supply, laying, and testing of one circuit and one conductor per phase featuring Al 18/30 kV RHZ1-OL 1×240 mm² cable.

Traction Substation (SETE): Supply, assembly, testing, and commissioning of the equipment integrating the SETE.

Depressed Section Transformation Center: Supply, assembly, testing, and commissioning of the equipment integrating the Depressed Section CT.