CLIENT:
Federal Electricity Commission (CFE)
CONTRACT AMOUNT:
174.70 Million USD
DESCRIPTION:
The project is being developed under a lump-sum, turnkey construction contract. Its scope encompasses the engineering, procurement, construction, testing, and commissioning of 300 km of transmission lines across the States of Sinaloa and Nayarit, including the expansion of 3 Substations:
Mazatlan II Substation: One Line exit bay + 4 Reactors at 400 kV.
Tepic II Substation: One 400 kV Line bay.
Cerro Blanco Substation: One 400 kV Line bay.
Mazatlan II – Tepic II Transmission Line: 256 km in length, 400 kV Transmission Line.